ŞİRVAN–SALYAN–NEFTÇALA STEEL PIPELINE PROJECT AZERBAIJAN / AZERSU

tamam-21

Construction Time : 6 months (July 2013 – December 2013)
Description of the Project : The work is renewal of drinking water pipeline which has 5936m length in total between Salyan and Neftçala town.
In the scope of this project, in total;
With ;
Ø1000mm 5851m,
85m Ø1200m,
Steel pipe fitting material supply has been completed. With reinforced concrete works project was delivered in December 2013.
Main Contractor : Texno-Atinak