Completed Projects
SUMQAYIT SANITATION COLLECTOR/PUMP STATION CONSTRUCTION SUMQAYIT/AZERBAIJAN / AZERSU
tamam-10
| Construction Time | : | 36 months (2011-2014) |
| Description of the Project | : | The work is; to collect sewage and drainage water which is drained off to sea from 30 points in Sumqayıt city by collecting it with sanitation line that will be constructed and removing the water from city center coast and bringing it to pump station which will be built.
In the scope of this project, in total ; Within Project 1, 4040m Ø1000mm GRP pipe , By making the preparation of the project and making the preparations of expropriation plans,the entire sewage water which free-flows to sea from Sumqayıt city coast has been brought to AAT TM pump station and from here it is pumped to available treatment plant. |
| Main Contractor | : | Texno –Atinak Partnership |