KESON WELL AND PUMPING STATION CONSTRUCTION AND VARIOUS INFRASTRUCTURE WORKS CONSTRUCTION / YALOVA/BURSA

tamam-26

Construction Time : 6 Months ( 2007)
Description of the Project : The work is ; with the aim of increasing the production capacity of Aksa Acrylic Chemical Inc., ensuring the supply of cooling water from the sea and making water intake filter construction.

In the scope of project; in the sea and on land ;
– Ø1200mm steel pipeline
– 14m diameter water intake and filter structure caissons construction
– Construction of front water intake pool
– Preparation of the applications and the business end projects,

These works have been completed and the system is activated.

Main Contractor : Atinak Engineering Construction Industry Trade Inc.